Job detail · stage-gate traveller
PE-10199 — Actuator End Cap Set
On TrackCustomer
Ridgeway Engineering
Order value
£61,500
Deposit received
£18,450
Current stage
Drawing Review
Status
On Track
Job traveller
Gate progression through pre-production
✓
Order
Cleared
●
Drawing Review
In gate
○
Engineering
Pending
○
Customer Approval
Pending
○
Procurement
Pending
○
Production Ready
Pending
○
Factory
Pending
Current stage
DRAWING REVIEW
Expected dwell3 days
Actual dwell3.8 days
Variance+0.8 days
OwnerFinance
Requested01 Jun
Expected09 Jun
Current16 Jun
Next milestoneReview complete
Manufacturing details
Vertical-specific operational state
Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released
Financial state
Capital consequence of the operational state
Capital currently exposed
£21,000
Deposit received£18,450
Next payment milestone£15,400
Expected release09 Jun
Projected release16 Jun
Release delay+1 days