PE-10231 — Sub-Frame Machining Pack

Complete

Customer

Northfield Industrial

Order value

£97,100

Deposit received

£29,150

Current stage

Factory

Status

Complete

Job traveller

Gate progression through pre-production

✓

Order

Cleared

✓

Drawing Review

Cleared

✓

Engineering

Cleared

✓

Customer Approval

Cleared

✓

Procurement

Cleared

✓

Production Ready

Cleared

●

Factory

In gate

Current stage

FACTORY

Expected dwell4 days
Actual dwell13.8 days
Variance+9.8 days
OwnerProcurement
Requested05 Jun
Expected13 Jun
Current07 Jun
Next milestoneFactory released

Manufacturing details

Vertical-specific operational state

Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released

Financial state

Capital consequence of the operational state

Capital currently exposed

£0

Deposit received£29,150
Next payment milestone£24,300
Expected release13 Jun
Projected release07 Jun
Release delay+10 days