Pre-production governance · Precision Engineering
Book a DiagnosticBA

Job detail · stage-gate traveller

PE-10240 — Actuator End Cap Set

On Track

Customer

Harlow Industrial Plant

Order value

£104,200

Deposit received

£31,250

Current stage

Customer Approval

Status

On Track

Job traveller

Gate progression through pre-production

✓

Order

Cleared

✓

Drawing Review

Cleared

✓

Engineering

Cleared

●

Customer Approval

In gate

○

Procurement

Pending

○

Production Ready

Pending

○

Factory

Pending

Current stage

CUSTOMER APPROVAL

Expected dwell5 days
Actual dwell3.7 days
Variance-1.3 days
OwnerProduction Planning
Requested07 Jun
Expected16 Jun
Current01 Jun
Next milestoneCustomer Approval complete

Manufacturing details

Vertical-specific operational state

Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released

Financial state

Capital consequence of the operational state

Capital currently exposed

£27,800

Deposit received£31,250
Next payment milestone£26,100
Expected release16 Jun
Projected release01 Jun
Release delay+0 days