Job detail · stage-gate traveller
PE-10256 — Precision Gearbox Housing
On TrackCustomer
Thornbury Process Systems
Order value
£57,200
Deposit received
£17,150
Current stage
Drawing Review
Status
On Track
Job traveller
Gate progression through pre-production
✓
Order
Cleared
●
Drawing Review
In gate
○
Engineering
Pending
○
Customer Approval
Pending
○
Procurement
Pending
○
Production Ready
Pending
○
Factory
Pending
Current stage
DRAWING REVIEW
Expected dwell4 days
Actual dwell4.3 days
Variance+0.3 days
OwnerCustomer
Requested03 Jun
Expected13 Jun
Current16 Jun
Next milestoneReview complete
Manufacturing details
Vertical-specific operational state
Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released
Financial state
Capital consequence of the operational state
Capital currently exposed
£20,700
Deposit received£17,150
Next payment milestone£14,300
Expected release13 Jun
Projected release16 Jun
Release delay+0 days