Pre-production governance · Precision Engineering
Book a DiagnosticBA

Job detail · stage-gate traveller

PE-10272 — Hydraulic Manifold Assembly

At Risk

Customer

Brackenridge Energy Systems

Order value

£58,500

Deposit received

£17,550

Current stage

Procurement

Status

At Risk

Job traveller

Gate progression through pre-production

✓

Order

Cleared

✓

Drawing Review

Cleared

✓

Engineering

Cleared

✓

Customer Approval

Cleared

●

Procurement

In gate

○

Production Ready

Pending

○

Factory

Pending

Current stage

PROCUREMENT

Expected dwell3 days
Actual dwell5.5 days
Variance+2.5 days
OwnerProcurement
Requested05 Jun
Expected07 Jun
Current05 Jun
Next milestoneProcurement complete

Blocker

Procurement dwell exceeded expected gate window

Manufacturing details

Vertical-specific operational state

Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released

Financial state

Capital consequence of the operational state

Capital currently exposed

£26,500

Deposit received£17,550
Next payment milestone£14,600
Expected release07 Jun
Projected release05 Jun
Release delay+3 days