Pre-production governance · Precision Engineering
Book a DiagnosticBA

Job detail · stage-gate traveller

PE-10431 — Actuator End Cap Set

On Track

Customer

Northfield Industrial

Order value

£42,500

Deposit received

£12,750

Current stage

Production Ready

Status

On Track

Job traveller

Gate progression through pre-production

✓

Order

Cleared

✓

Drawing Review

Cleared

✓

Engineering

Cleared

✓

Customer Approval

Cleared

✓

Procurement

Cleared

●

Production Ready

In gate

○

Factory

Pending

Current stage

PRODUCTION READY

Expected dwell2 days
Actual dwell1.8 days
Variance-0.2 days
OwnerProduction Planning
Requested11 Jun
Expected13 Jun
Current13 Jun
Next milestoneFactory release

Manufacturing details

Vertical-specific operational state

Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released

Financial state

Capital consequence of the operational state

Capital currently exposed

£8,200

Deposit received£12,750
Next payment milestone£10,600
Expected release13 Jun
Projected release13 Jun
Release delay+0 days