Job detail · stage-gate traveller
PE-10445 — Machined Valve Body
On TrackCustomer
Thornbury Process Systems
Order value
£60,400
Deposit received
£18,100
Current stage
Engineering
Status
On Track
Job traveller
Gate progression through pre-production
✓
Order
Cleared
✓
Drawing Review
Cleared
●
Engineering
In gate
○
Customer Approval
Pending
○
Procurement
Pending
○
Production Ready
Pending
○
Factory
Pending
Current stage
ENGINEERING
Expected dwell3 days
Actual dwell4.2 days
Variance+1.2 days
OwnerCustomer
Requested07 Jun
Expected01 Jun
Current07 Jun
Next milestoneEngineering complete
Manufacturing details
Vertical-specific operational state
Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released
Financial state
Capital consequence of the operational state
Capital currently exposed
£16,600
Deposit received£18,100
Next payment milestone£15,100
Expected release01 Jun
Projected release07 Jun
Release delay+1 days