Job detail · stage-gate traveller
PE-10449 — Spindle Carrier Assembly
BlockedCustomer
Ridgeway Engineering
Order value
£117,600
Deposit received
£35,280
Current stage
Customer Approval
Status
Blocked
Job traveller
Gate progression through pre-production
✓
Order
Cleared
✓
Drawing Review
Cleared
✓
Engineering
Cleared
●
Customer Approval
In gate
○
Procurement
Pending
○
Production Ready
Pending
○
Factory
Pending
Current stage
CUSTOMER APPROVAL
Expected dwell3 days
Actual dwell11.4 days
Variance+8.4 days
OwnerCustomer
Requested31 May
Expected03 Jun
Current15 Jun
Next milestoneDrawing approval
Blocker
Drawing approval outstanding — customer design freeze pending
Manufacturing details
Vertical-specific operational state
Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released
Financial state
Capital consequence of the operational state
Capital currently exposed
£39,800
Deposit received£35,280
Next payment milestone£29,400
Expected release03 Jun
Projected release15 Jun
Release delay+12 days