Job detail · stage-gate traveller
PE-10472 — Hydraulic Manifold Assembly
At RiskCustomer
Brackenridge Energy Systems
Order value
£86,800
Deposit received
£26,050
Current stage
Procurement
Status
At Risk
Job traveller
Gate progression through pre-production
✓
Order
Cleared
✓
Drawing Review
Cleared
✓
Engineering
Cleared
✓
Customer Approval
Cleared
●
Procurement
In gate
○
Production Ready
Pending
○
Factory
Pending
Current stage
PROCUREMENT
Expected dwell4 days
Actual dwell6.2 days
Variance+2.2 days
OwnerEngineering
Requested16 Jun
Expected03 Jun
Current07 Jun
Next milestoneProcurement complete
Blocker
Procurement dwell exceeded expected gate window
Manufacturing details
Vertical-specific operational state
Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released
Financial state
Capital consequence of the operational state
Capital currently exposed
£32,800
Deposit received£26,050
Next payment milestone£21,700
Expected release03 Jun
Projected release07 Jun
Release delay+2 days