Pre-production governance · Precision Engineering
Book a DiagnosticBA

Job detail · stage-gate traveller

PE-10495 — Actuator End Cap Set

Complete

Customer

Sterling Engineering Services

Order value

£57,400

Deposit received

£17,200

Current stage

Factory

Status

Complete

Job traveller

Gate progression through pre-production

✓

Order

Cleared

✓

Drawing Review

Cleared

✓

Engineering

Cleared

✓

Customer Approval

Cleared

✓

Procurement

Cleared

✓

Production Ready

Cleared

●

Factory

In gate

Current stage

FACTORY

Expected dwell5 days
Actual dwell3.9 days
Variance-1.1 days
OwnerFinance
Requested05 Jun
Expected05 Jun
Current11 Jun
Next milestoneFactory released

Manufacturing details

Vertical-specific operational state

Drawing revisionRev 04
Tolerance reviewComplete
Engineering hours26 / 32
ToolingRequired
Material316L Stainless Steel
ProcurementNot released

Financial state

Capital consequence of the operational state

Capital currently exposed

£0

Deposit received£17,200
Next payment milestone£14,400
Expected release05 Jun
Projected release11 Jun
Release delay+0 days