Pre-production governance · Precision Engineering
Book a DiagnosticBA

Exception · capital impact

Drawing Review Delay

PE-10252 — Actuator End Cap Set

At Risk

Operational issue

Owner: Finance

Drawing Review dwell exceeded expected gate window

Expected dwell3 days
Actual dwell5.7 days
Variance+2.7 days

Causal chain

Operational state → capital consequence

  1. DRAWING REVIEW DELAY
  2. PRODUCTION RELEASE DELAY
  3. PAYMENT MILESTONE DELAY
  4. LONGER CASH CONVERSION
  5. CAPITAL REMAINS TIED UP

Why this matters

This order cannot progress to the next release condition until the gate is cleared. The resulting dwell increases the amount of capital tied up before factory release, pushes the next payment milestone out by 3 days and extends the cash conversion cycle for the whole portfolio.

Recommended action

Clear the drawing review gate and release the job to the next stage.

Back to job

Capital at risk

£5,500

held in pre-production against this order

Order value£23,600
Deposit received£7,100
Next payment milestone£5,900
Projected milestone delay3 days
Current pre-production exposure£5,500