Pre-production governance · Precision Engineering
Book a DiagnosticBA

Exception · capital impact

Engineering Delay

PE-10279 — Actuator End Cap Set

Blocked

Operational issue

Owner: Engineering

Engineering dwell exceeded expected gate window

Expected dwell4 days
Actual dwell14.2 days
Variance+10.2 days

Causal chain

Operational state → capital consequence

  1. ENGINEERING DELAY
  2. PRODUCTION RELEASE DELAY
  3. PAYMENT MILESTONE DELAY
  4. LONGER CASH CONVERSION
  5. CAPITAL REMAINS TIED UP

Why this matters

This order cannot progress to the next release condition until the gate is cleared. The resulting dwell increases the amount of capital tied up before factory release, pushes the next payment milestone out by 10 days and extends the cash conversion cycle for the whole portfolio.

Recommended action

Clear the engineering gate and release the job to the next stage.

Back to job

Capital at risk

£6,600

held in pre-production against this order

Order value£26,800
Deposit received£8,050
Next payment milestone£6,700
Projected milestone delay10 days
Current pre-production exposure£6,600