Exception · capital impact
Drawing Review Delay
PE-10329 — Sub-Frame Machining Pack
Operational issue
Owner: Procurement
Drawing Review dwell exceeded expected gate window
Expected dwell4 days
Actual dwell11.5 days
Variance+7.5 days
Causal chain
Operational state → capital consequence
- DRAWING REVIEW DELAY
- PRODUCTION RELEASE DELAY
- PAYMENT MILESTONE DELAY
- LONGER CASH CONVERSION
- CAPITAL REMAINS TIED UP
Why this matters
This order cannot progress to the next release condition until the gate is cleared. The resulting dwell increases the amount of capital tied up before factory release, pushes the next payment milestone out by 8 days and extends the cash conversion cycle for the whole portfolio.
Recommended action
Clear the drawing review gate and release the job to the next stage.
Capital at risk
£25,000
held in pre-production against this order
Order value£63,300
Deposit received£19,000
Next payment milestone£15,800
Projected milestone delay8 days
Current pre-production exposure£25,000