Pre-production governance · Precision Engineering
Book a DiagnosticBA

Exception · capital impact

Procurement Delay

PE-10439 — Sub-Frame Machining Pack

At Risk

Operational issue

Owner: Production Planning

Procurement dwell exceeded expected gate window

Expected dwell4 days
Actual dwell6.1 days
Variance+2.1 days

Causal chain

Operational state → capital consequence

  1. PROCUREMENT DELAY
  2. PRODUCTION RELEASE DELAY
  3. PAYMENT MILESTONE DELAY
  4. LONGER CASH CONVERSION
  5. CAPITAL REMAINS TIED UP

Why this matters

This order cannot progress to the next release condition until the gate is cleared. The resulting dwell increases the amount of capital tied up before factory release, pushes the next payment milestone out by 2 days and extends the cash conversion cycle for the whole portfolio.

Recommended action

Clear the procurement gate and release the job to the next stage.

Back to job

Capital at risk

£23,600

held in pre-production against this order

Order value£74,700
Deposit received£22,400
Next payment milestone£18,700
Projected milestone delay2 days
Current pre-production exposure£23,600