Pre-production governance · Precision Engineering
Book a DiagnosticBA

Exception · capital impact

Engineering Revision Delay

PE-10476 — Precision Gearbox Housing

At Risk

Operational issue

Owner: Engineering

Engineering revision in progress — tolerance stack rework

Expected dwell3 days
Actual dwell5.4 days
Variance+2.4 days

Causal chain

Operational state → capital consequence

  1. ENGINEERING DELAY
  2. PRODUCTION RELEASE DELAY
  3. PAYMENT MILESTONE DELAY
  4. LONGER CASH CONVERSION
  5. CAPITAL REMAINS TIED UP

Why this matters

This order cannot progress to the next release condition until the gate is cleared. The resulting dwell increases the amount of capital tied up before factory release, pushes the next payment milestone out by 4 days and extends the cash conversion cycle for the whole portfolio.

Recommended action

Clear the engineering gate and release the job to the next stage.

Back to job

Capital at risk

£27,100

held in pre-production against this order

Order value£84,200
Deposit received£25,260
Next payment milestone£21,050
Projected milestone delay4 days
Current pre-production exposure£27,100